Briefing

170,000 sq-ft hospital located in Cornelius, NC. Hospital has a 24-hour emergency department, 30 patient beds, maternity suites, two operating rooms, and an intensive care unit with four ICU beds.

ASC Equipment provided seismic engineering and vibration isolation for Mechanical, Electrical, and Plumbing systems and equipment.

Project

Atrium Health Lake Norman Hospital
Cornelius, NC

What We Did

ASC Equipment Provided:

  • Provided seismic bracing for all MEP systems including piping, duct, conduit, cable tray, and suspended equipment
  • Provided all design and anchorage for MEP equipment
  • Provided all specified vibration isolation components for Mechanical equipment
  • Identified/designed/provided seismic “V” loops on Mechanical and Plumbing systems for all building joints
  • Designed and provided spring isolated structural steel frame for the cooling towers
  • Provided all seismic/wind rated support rails for roof mounted pipe and duct including roof penetration curbs
  • Provided onsite training including routine site visits to review installation to aid contractors in preparation for 3rd party inspections

Seismic Bracing

Provided seismic bracing for Mechanical, Electrical, and Plumbing equipment.

Vibration Isolation

Provided vibration isolation for Mechanical Systems and Equipment.

Expansion Loops

Identified/designed/provided seismic “V” Loops for all building joints.

Seismic Rated Roof Curbs

Designed and provided seismic rated roof curbs for roof mounted pipe and duct including roof penetration curbs.